By: F. Wayne Nadon, Project Manager
PLACE: Shasta College Board Room
DATE: February 12, 2003
PURPOSE: PROJECT’S STATUS UPDATE
SUBJECT ACTION
I. UNIVERSITY CENTER PROJECT:
A. STATUS:
a. Siting and program schematic have been developed outlining the scope
and content of building.
b. Architect to present Schematic Design (including site and building
layouts/elevations)
B. PROJECT COST SUMMARY UPDATE:
Approved Budget amount: $6,500,000.
a. Design/Fees/Testing $ 997,274
b. Construction $ 4,025,000
c. Site work $ 825,000
d. Equipment (voice,data,fire alarms) $ 50,000
e. Contingency $ 600,000
Estimated Total Project Cost: $6,497,274
C. PROJECT SCHEDULE UPDATE:
Act. ID DESCRIPTION DURATION %Complete START FINISH
PROG SITING / PROGRAM 151 100 15JUL02 12FEB03
SD SCHEMATIC DEV. 32 0 12FEB03* 27MAR03
DD DESIGN DEV. 40 0 28MAR03 22MAY03
CD CONSTRUCTION DOC. 200 0 23MAY03 27FEB04
BID BID PHASE 40 0 02MAR04 23APR04
CP CONSTRUCTION PHASE 387 0 26APR04 20OCT05
* Board approval of U.C and Library Elevations is critical for Design
Development phase to begin on Library
Contact Person -